# Activity: Assign project roles and responsibilities in a RACI chart

1. Did you complete this activity?
    
    * <mark>Yes</mark>
        
    * No
        
2. **In the RACI model, which role reviews the work to confirm it is complete?**
    
    * Responsible
        
    * <mark>Accountable</mark>
        
    * Consulted
        
    * Informed
        
3. **What key questions should you consider when deciding who should be** `consulted` **about a task? Select all that apply.**
    
    * <mark>Who can give feedback to responsible individuals to help them complete tasks?</mark>
        
    * Finding out who can give feedback on task completion helps you determine who should be consulted.
        
    * Which department manages the work?
        
    * <mark>Who are the subject matter experts (SMEs) for the task?</mark>
        
    * Who might delegate the work to another team member?
        
4. I**n your completed RACI chart, how many stakeholders are accountable for the “code the landing page” task?**
    
    * 0
        
    * <mark>1</mark>
        
    * 2 or more
        
5. **In your completed RACI chart, who is** `responsible` **for testing the landing page?**
    
    * The Web Manager
        
    * The Web Designer
        
    * <mark>The Quality Assurance Tester</mark>
        
    * The Web Developer
        

---